Casa Adelante — 2828 16th Street
Project status · In operation
- Sponsor / Developer
- TNDC + MEDA
- Bond Issuer
- City and County of San FranciscoAgency approval · authorized issuer
- Local Jurisdiction
- San Francisco
- Current Status
- In operationDeveloper representation · current property status
Casa Adelante is an operating 143-home affordable housing development in San Francisco’s Mission District, co-developed by TNDC and MEDA. The development serves families and individuals at 40–60% AMI.Project description
Project Details
Casa Adelante is an operating 143-home affordable housing development in San Francisco’s Mission District, co-developed by TNDC and MEDA. The development serves families and individuals at 40–60% AMI.Project description
- Neighborhood
- Mission District
Public Commitments & Benefits
A. Affordability Commitments
- Restricted homes
- 143 of 143 homes (100.0%)Project-team information retained from existing record
- AMI targeting
- 40–60% AMIProject description / supplied project information
Why these restrictions apply
B. Public Investment & Support
Bond allocation authorizes tax-exempt financing. Tax credits support investor equity; rental assistance supports eligible residents. These programs have distinct roles.
- Public financing / support
- LIHTC equity
- Public financing / support
- Tax-exempt bonds
- Public financing / support
- San Francisco Mayor’s Office of Housing and Community Development (MOHCD)
- Public financing / support
- Federal Home Loan Bank Affordable Housing Program (FHLB/AHP)
- Public financing / support
- Private financing
C. Additional Project Benefits
Committed Project Features
Project Characteristics
- Features
- Rooftop urban farm; Affordable childcare; Community rooms; Neighborhood nonprofit spaceProject description / supplied project information
Public Investment & Financing
Allocation & Financing Amounts
- Financing
- LIHTC equity · Tax-exempt bonds · San Francisco Mayor’s Office of Housing and Community Development (MOHCD) · Federal Home Loan Bank Affordable Housing Program (FHLB/AHP) · Private financingProject description / supplied project information
Financing Participants
- Financing participant
- Bank of America — LIHTC equity
- Financing participant
- Tax-exempt bonds
- Financing participant
- MOHCD
- Financing participant
- FHLB/AHP through Century Housing
- Financing participant
- Barings / MassMutual
Public Record Trail
- Initial TCO — August 6, 2021
- 103 units certified for occupancyApplication 201707051030 · issued 2021-08-06 · retrieved 2026-10-02
- Amended TCO — August 20, 2021
- 40 additional units certified for occupancyApplication 201707051030 · issued 2021-08-20 · retrieved 2026-10-02
- DBI Permit Marked Complete — December 21, 2021
- Administrative permit completion dateApplication 201707051030 · City record as of 2025-08-07 · retrieved 2026-10-02
- Building Permit Issued — August 31, 2018
- 201707051030Application 201707051030 · City record as of 2025-08-07 · retrieved 2026-10-02
Building & Occupancy Status
- Building Permit Application Number
- 201707051030Application 201707051030 · City record as of 2025-08-07 · retrieved 2026-10-02
- Current DBI Permit Status
- completeApplication 201707051030 · City record as of 2025-08-07 · retrieved 2026-10-02
- DBI Status Date
- December 21, 2021Application 201707051030 · City record as of 2025-08-07 · retrieved 2026-10-02
- Permit Issuance Date
- August 31, 2018Application 201707051030 · City record as of 2025-08-07 · retrieved 2026-10-02
- Total Project Units
- 143
- Initial TCO Date
- August 6, 2021Application 201707051030 · Initial TCO issued 2021-08-06 · retrieved 2026-10-02
- Amended TCO Date
- August 20, 2021Application 201707051030 · Amended TCO issued 2021-08-20 · retrieved 2026-10-02
- Units Certified for Occupancy
- 143Application 201707051030 · sum of units certified in Initial / Amended TCO / CFC rows · retrieved 2026-10-02
- Final Construction Completion
- Not separately verified
- DBI Permit Completion Date
- December 21, 2021Application 201707051030 · City record as of 2025-08-07 · retrieved 2026-10-02
- Latest Addenda / Routing Event
- June 29, 2021 · CPB · errcs. · issuedApplication 201707051030 · addenda 5 · station CPB · event 2021-06-29 · record as of 2025-06-23 · retrieved 2026-10-02
- Source Data Checked
- October 2, 2026
Public Documents & Sources
· Project sponsor
View DocumentUsed for: Project description
Source Locations
- Project overview
Checked October 1, 2026 · Tenderloin Neighborhood Development Corporation
View DocumentUsed for: Existing project status and description
Source Locations
- Property status / project overview
· City and County of San Francisco
View DocumentUsed for: Authorized bond issuer; approval does not establish final issuance
Source Locations
- Resolution title / legislative history
2026-10-02 · San Francisco Department of Building Inspection / DataSF
View DocumentUsed for: Application identity, exact DBI administrative status, issuance and administrative completion dates
Source Locations
- Application 201707051030 · retrieved 2026-10-02
- record_id 1469276157982 · data_as_of 2025-08-07T23:55:01.000
- Matched City address: 1990 Folsom St
2026-10-02 · San Francisco Department of Building Inspection / DataSF
View DocumentUsed for: Occupancy certificate types, dates and cumulative units certified
Source Locations
- Application 201707051030 · retrieved 2026-10-02
- Initial TCO · 2021-08-06 · 103 units · 1990 Folsom Street
- Amended TCO · 2021-08-20 · 40 units · 1990 Folsom Stret
- Monthly changes in certified units; zero-additional-unit CFC and amended TCO documents are omitted.
2026-10-02 · San Francisco Department of Building Inspection / DataSF
View DocumentUsed for: Latest recorded addenda / routing event; routing reviews are not final inspections
Source Locations
- Application 201707051030 · retrieved 2026-10-02
- Application 201707051030 · addenda 5 · station CPB · event 2021-06-29 · record as of 2025-06-23 · retrieved 2026-10-02